Over the next few years, we will be investing in the water network in Herefordshire to ensure we provide customers with clean fresh drinking water for years to come. To do this we will be renewing and clearing around 125km of pipe.  Below is information on the individual projects which form part of the investment.

 


Westhide

Street names: A465 at the junction by Morris Corfield and Co, and will continue until it reaches the next junction which is the turning to Ocle Pychard past Phil Jones Vans.

Start date: 8th May 2018

Expected completion date: Mid July 2018

Additional information: Our contract partners, O’Connor Utilities will be carrying out this work on our behalf. Work will start on 8th May 2018 and we anticipate this being completed by mid-July 2018. The work will start on the A465 at the junction by Morris Corfield and Co, and will continue until it reaches the next junction which is the turning to Ocle Pychard past Phil Jones Vans. In order to carry out this work safely and quickly and to ensure we keep traffic flowing, the work will be undertaken with two way traffic lights. These will move with us as the work progresses.


Yazer Road, Moor Farm and surrounding areas.

Street names: Yazer Road and Moor Farm

Start date: 18th September 2017

Expected completion date: End of May 2018

Additional information:  In order to carry this work out safely there will be some traffic management in place throughout the work but we’ll try to keep this to an absolute minimum and maintain access for residents. In this area it will involve replacing over 3.4 kilometres of pipe. We would like to thank people in advance for bearing with us.

Our contract partners, O’Connor Utilities have already completed our work in Windemere Road. After the Christmas break you will see our work begin in Sheridan Road and Hurdman Walk around the 8th January 2018. We anticipate this work taking approximately 14 weeks to complete.

Work Ongoing:
• Work is currently ongoing in Sheridan Road.
• Work is currently ongoing in Hurdman Walk.
• Work is currently ongoing in Clivedon Grove.

Work Completed:
• Windermere Road
• Derwent Drive
• Coniston Walk


Whittern Way

Street names: Whittern Way

Start date: 18th September 2017

Expected completion date: End of May 2018

Additional information:  In order to carry this work out safely there will be some traffic management in place throughout the work but we’ll try to keep this to an absolute minimum and maintain access for residents. In this area it will involve replacing over 3.2 kilometres of pipe. We would like to thank people in advance for bearing with us.

Our contract partners, O’Connor Utilities have already started our work in Whittern Way, and after the Christmas break you will see our work begin in Prospect Walk. Before Christmas we will prepare our work site in Prospect Walk, with work starting on January 8th 2018. This work will take approximately 12 weeks to complete.

Work Ongoing:
• Work is currently ongoing in Prospect Walk.
• Work is currently ongoing in Grandison Rise.

Work Completed: