Dŵr Cymru Welsh Water reports that investment in south east Wales during 2011/12 reached £68m – and a further spend of £71m is underway this year to maintain top quality services to customers.

Announcing its financial results for the past year, Welsh Water reported that its spending programme is on track to deliver an ambitious £1billion boost to water services infrastructure throughout its area over the next three years. 

Spending in south east Wales during 2011/12 on maintenance programmes for the company’s drinking water and wastewater systems totalled £39m, with £12m spent on delivering drinking water quality and environmental improvements. Investment of £3m was made supporting economic growth by ensuring adequate network capacity for new developments and a further £5m was invested to alleviate the risk of sewage flooding to properties.

Investment was also completed on a £40m advanced anaerobic digestion facility at Cardiff wastewater treatment works. The facility extracts methane gas from wastewater which is then used to produce 21 million kilowatts of electricity a year – the equivalent of powering 4,000 homes. Reduction in reliance on power from fossil fuels enables Dŵr Cymru to keep down customers’ bills.

The area also benefited from part of a £9m investment across the whole of south Wales to reduce leakage from the company’s massive network of water pipes.

Dŵr Cymru Welsh Water managing director Nigel Annett said, “We are investing heavily in projects in south east Wales, upgrading the wastewater network to both minimise the impact of our operations on the environment and also protect properties from the risk of sewer flooding.

“During 2011/12 investment was made on improving and increasing the capacity of trunk sewers. We are continuing with a similar level of investment in this area during 2012/13, focusing on improvements to operating processes at wastewater treatment works, providing new sewerage connections as well as further sewer flooding alleviation schemes. Investment is also set to continue to protect and improve drinking water quality.

“Our investment in wastewater treatment is benefiting the environment by helping to improve rivers and coastal bathing water quality – which contributes to the number of Blue Flag beaches that we have in Wales.”

Highlights of investment in 2011/12 also included major wastewater schemes in Caerphilly and Powys. Also, a £2.4m investment replacing 3.6km of new sewer pipe between Deri and Bargoed was completed. This was essential work to upgrade the public wastewater network in the area and improve the water quality of the Rhymney River.

Further investment of £71m is already underway or planned in south east Wales for the present financial year 2012/13. £52m is being spent on maintenance works, with £10m for drinking water quality and environment improvements. Investment of £2m is planned to support economic growth by ensuring network capacity for new developments, with a further £7m allocated to schemes to alleviate the risk of sewage flooding of properties.

Welsh Water is a ‘not-for-profit company’ which has been owned by Glas Cymru since 2001. It does not have shareholders, and any financial surpluses are reinvested in the business for the benefit of customers.

Click here to view a map of the investment.

Ends

Enquiries to the Dwr Cymru Welsh Water press office on 029 2055 6140

Notes to editors

Highlights for the year

Financial results

Customer service

Environment

Bookmark with: