Torfaen

Man drinking waterOver the next few years, we will be investing over £1.2 million in Torfaen (and Newport) on the water network to provide customers with clean, fresh water for years to come. The work will see us replacing or clearing over 21km of pipe. Below is information on the individual schemes that will form part of the investment.


Ty Coch

Street name: Two Locks Road and Ty Coch Way

Expected start date: July 2016

Expected completion date: October 2016

Additional information: A road closure will be in place on Two Locks Road for around 6 weeks from 20 July, however access for residents will be maintained as much as possible. Temporary traffic lights will then be in place for 6 weeks on Ty Coch Way following work on Two Locks Road. We would like to thank you for bearing with us.

 

Water quality investment work video: