Flintshire

Man drinking waterWe are investing over £6 million in the water network in north east Wales to ensure we provide customers with clean fresh drinking water for years to come. To do this we will be renewing and clearing around 60km of pipe.  Below is information on the individual projects which form part of the investment.


Sandycroft

Street names: Fairway, Lawrence Street, Hamilton Avenue, North Street, Phoenix Street - Completed

Start date: June 2016

Expected completion date: October 2016

Additional information: There will be traffic lights on Phoenix Way for the duration of the work.  Temporary road closures will also be necessary on the streets above but we will be writing to customers living there to give advance notice and details of any diversion routes that may be necessary.  We would like to thank people in advance for bearing with us.

We will also be at Phoenix Street Methodist Church coffee morning between 10.30am – 11.30am every other Friday (from 12th  August).


Connah’s Quay

Street names: Beechwood Avenue, Celyn Avenue, Deva Street, Englefield Avenue, Fairfield Avenue, Gornel Avenue, Linden Avenue, Lynfield Close, Merllyn Avenue, Pinewood Avenue, St David’s Drive, Hillside Avenue, St Mark’s Avenue, Summerfield Close, Bryn Road, Upper Bryn Road, River View.

Start date: June 2016

Expected completion date: February 2017

Additional information: Temporary road closures will be necessary on the streets above during the work but we will be writing to customers living there to give advance notice and details of any diversion routes that may be necessary.  We would like to thank people in advance for bearing with us.


Street names: Eaton Ave, Henley Ave, Marlowe Avenue, Park Grove, Poplar Close, Richmond Road, Thornfield Avenue, Wepre Hall Crescent, Windsor Ave

Expected start date: October2016

Expected completion date: March 2017

Additional information: Temporary road closures will be necessary on the streets above during the work but we will be writing to customers living there to give advance notice and details of any diversion routes that may be necessary.  We would like to thank people in advance for bearing with us.


Bagillt

Street names: Wern Avenue, Bron Avenue - Completed

Start date: July 2016

Expected completion date: October 2016

Additional information: Temporary road closures will be necessary on the streets above during the work but we will be writing to customers living there to give advance notice and details of any diversion routes that may be necessary.  We would like to thank people in advance for bearing with us.


Street names: Ash Grove, Manor Drive, Oak Grove - Completed

Expected start date: August 2016

Expected completion date: November 2016

Additional information: Temporary road closures will be necessary on the streets above during the work but we will be writing to customers living there to give advance notice and details of any diversion routes that may be necessary.  We would like to thank people in advance for bearing with us.


Buckley

Street name: Tram Road

Start date: November 2016

Expected completion date: December 2016

Additional information: We will need to implement a road closure on Tram Road to carry out the work safely. We would like to thank people in advance for bearing with us.


Street name: Bryn Road - Completed

Start date: July 2016

Expected completion date: September 2016

Additional information: We will need to implement a road closure on Bryn Road to carry out the work safely.  We would like to thank people in advance for bearing with us.


Street name: Aberllanerch Drive and Birkdale Avenue - Completed

Start date: September 2016

Expected completion date: November 2016

Additional information: Temporary road closures will be necessary on the streets above during the work but we will be writing to customers living there to give advance notice and further details. We would like to thank people in advance for bearing with us.


Queensferry

Street name: Aston Road

Start date: November 2016

Expected completion date: December 2017

Additional information: We will need to have traffic lights in place on Aston Road to carry out the work safely.  We would like to thank people in advance for bearing with us.


Mold

Street names: Llanasa Road & Sarn Road

Start date: October 2016

Expected completion date: November 2016

Additional information: We would like to thank people in advance for bearing with us. Llanasa Road & Sarn Road will be closed to through traffic during the dates shown with local diversions in place. We will make sure that advanced warning signs go up so that you have plenty of notice.


Street names: Bromfield Lane, Queens Lane - Completed

Start date: June 2016

Expected completion date: September 2016

Additional information: We will need to have temporary road closures in place on Bromfield Lane and Queen’s Lane and customers living there will have received information about this.  We would like to thank people for bearing with us.


Mancot, Deeside

Street name: Gladstone Way

Start date: November 2016

Expected completion date: March 2017

Additional information: So the work can be done safely and efficiently, traffic lights will be in place on Gladstone Way. We’re sorry for any disruption this may cause, thank you for bearing with us.


Tre Mostyn, Holywell (Plas Uchaf)

Street name: Plas Uchaf Junction to Tre Mostyn Junction & Pentre Ffynnon Farm Junction to Tre Mostyn Junction

Start date: November 2016

Expected completion date: January 2017

Additional information: We would like to thank people in advance for bearing with us. There will be a road closure will be in place from 21/11/2016 – 03/02/2016 (The road will be re-opened to traffic over the Christmas and New Year Period). We’re sorry for any disruption this may cause.


Water quality investment work video: