YOU ARE HERE > Home > Community including education & recreation > Investment

Cliciwch yma i weld y fersiwn Cymraeg

Click here to subscribe to RSS

North Wales Investment

How to contact us

  • General enquiries - Click here to email us or call 0800 052 0145
corner

Facilities that will benefit from our investment

Facilities that will benefit from our investment Cilfor Bryn Cowlyd Alwen Capel Curig
Mynydd Llandygai Cwellyn Cwm Dulyn Cwmystradllyn Eithinfynydd Llannerch/Glascoed LlidiardauBala Rhiwgoch Pen y Cefn

Keeping you up to date

The overall £100 million investment programme is being progressed as quickly as possible, most of the projects are scheduled to be completed in the period 2010-2015, although the design work for several of the sites, including Mynydd Llandygai, is well advanced and construction is due to start here in the new year.

Alwen

Denbigh, Ruthin, Cerrigydrudion, Llandrillo, Corwen, Glyndyfyrdwy, Llanarmon (supports Queensferry, Buckley etc)

Investment
New water treatment works - £12.2m

Work proposed
Replace existing filtration plant

Benefits
Improve effectiveness of filtration to deal with manganese and aluminium in raw water

Completion by: June 2013

Bryn Cowlyd

Llanrwst, Llandudno, Colwyn Bay, Llanddulas, Llansannan, Llanfair Talhaearn

Investment
New water treatment works - £3.5m, UV and chloramination

Work proposed
UV to be installed. Build new treatment stage to clarify the water before existing filtration

Benefits
UV deactivates any cryptosporidium oocysts in the water.
New treatment stage will deal with changing raw water conditions and consistently meet all water quality standards.

Completion by: UV Dec 2009
New Water Treatment Works Dec 2014

Capel Curig


Investment
UV treatment - £2.1m

Work proposed
UV to be installed

Benefits
UV deactivates any cryptosporidium oocysts in the water.

Completion by: UV installed Feb 2009

Cilfor

Porthmadog, Penrhyndeudraeth, Croesor

Investment
UV treatment - £0.4m, New water treatment works - £4.8m

Work proposed
UV to be installed. Build new treatment stage to clarify the water before existing filtration

Benefits
UV deactivates any cryptosporidium oocysts in the water.
New treatment stage will deal with changing raw water conditions and consistently meet all water quality standards.

Completion by: UV installed Feb 2009
New Water Treatment Works Sept 2011

Cwellyn

Beddgelert, Penygroes, Caernarfon, Llanberis, Bangor, South Anglesey, Bethesda

Investment
New water treatment works - £14m

Work proposed
UV already installed.
Build new treatment stage to clarify water before existing filtration

Benefits
UV deactivates any cryptosporidium oocysts in the water.
New treatment stage will deal with changing raw water conditions and consistently meet all water quality standards.

Completion by: UV installed Sept 2008
New Water Treatment Works March 2010

Cwm Dulyn

Nebo, Bwlch Derwin; Glynnog Fawr

Investment
UV treatment - £0.6m

Work proposed
UV to be installed

Benefits
UV deactivates any cryptosporidium oocysts in the water.

Completion by: UV installed Feb 2009

Cwmystradllyn

Porthmadog, Criccieth, Trefor, Lleyn Peninsula

Investment
New water treatment works - £13.2m, UV Treatment - £1.2m

Work proposed
UV to be installed. Build new treatment stage to clarify the water before existing filtration

Benefits
UV deactivates any cryptosporidium oocysts in the water.
New treatment stage will deal with changing raw water conditions and consistently meet all water quality standards.

Completion by: UV May 2009
New Water Treatment Works Dec 2013

Eithinfynydd

Llanbedr, Dyffryn Ardudwy, Llanaber, Barmouth

Investment
New water treatment works - £8m, UV Treatment - £0.4m

Work proposed
UV to be installed. Build new treatment stage to clarify the water before existing filtration

Benefits
UV deactivates any cryptosporidium oocysts in the water.
New treatment stage will deal with changing raw water conditions and consistently meet all water quality standards.

Completion by: UV installed Feb 2009
New Water Treatment Works March 2011

Llannerch/Glascoed

Abergele, Towyn, Rhyl, Rhuddlan, St Asaph, Rhuallt, Bodfari, Trefnant, Bodelwyddan

Investment
New water treatment works - £15m, UV Treatment - £0.7m

Work proposed
UV to be installed. Build new treatment stage to clarify the water before existing filtration

Benefits
UV deactivates any cryptosporidium oocysts in the water.
New treatment stage will deal with changing raw water conditions and consistently meet all water quality standards.

Completion by: UV installed Feb 2009
New Water Treatment Works June 2013

Llidiardau, Bala

Bala, Llanuwchlyn, Cefn Ddwysan, Llandderfel

Investment
New water treatment works - £8m, UV Treatment - £0.4m

Work proposed
UV to be installed. Build new treatment stage to clarify the water before existing filtration

Benefits
UV deactivates any cryptosporidium oocysts in the water.
New treatment stage will deal with changing raw water conditions and consistently meet all water quality standards.

Completion by: UV installed Feb 2009
New Water Treatment Works Sept 2012

Mynydd Llandygai

Beddgelert, Penygroes, Caernarfon, Llanberis, Bangor, South Anglesey, Deiniolen, Bethesda

Investment
New water treatment works - £10.9m, UV Treatment - £0.2m

Work proposed
UV already installed. Build new treatment stage to clarify water before existing filtration

Benefits
UV deactivates any cryptosporidium oocysts in the water.
New treatment stage will deal with changing raw water conditions and consistently meet all water quality standards.

Completion by: UV installed Sept 2008
New Water Treatment Works Sept 2010

Pen y Cefn

Dolgellau, Rhydymain, Llanfachreth, Ganllwyd, Brithdir, Bont Ddu, Fairbourne

Investment
New water treatment works - £8.6m, UV Treatment - £0.5m

Work proposed
UV to be installed. Build new treatment stage to clarify the water before existing filtration

Benefits
UV deactivates any cryptosporidium oocysts in the water.
New treatment stage will deal with changing raw water conditions and consistently meet all water quality standards.

Completion by: UV installed Feb 2009
New Water Treatment Works June 2011

Rhiwgoch

Harlech, Llanfair

Investment
UV £0.8m
New water treatment works £8.4m
New water mains £3.0m

Work proposed
UV to be installed.
Build new treatment stage to clarify the water before existing filtration
New link main and replacement of existing raw water main

Benefits
UV deactivates any cryptosporidium oocysts in the water.
New treatment stage will deal with changing raw water conditions and consistently meet all water quality standards.
Increase in works capacity to secure water supplies during high demand

Completion by: UV installed Feb 2009
New Water Treatment Works March 2010

corner

Further information

The map (left) shows all the treatment facilities in the north Wales area that will benefit from our investment programme.